Bloor Street Construction

Bloor Street Transformation Update

Yonge Street to Avenue Road:

All the major reconstruction components on the southern portion, of the roadway and sidewalk between Yonge and Bay Streets will be completed today and construction work on the north side of this section of the roadway and boulevard will commence on Monday, May 17, to include excavation of the sidewalk by mid week.   The intersection of Balmuto and Bloor Street is expected to be reopened.

The installation of granite sidewalk is continuing on the south side, west of Bay Street and excavation work and soil cell installation is being carried out towards Avenue Road.

Church Street to Yonge Street:

Hydro Vault work is near completion at 81 Bloor Street East and continues at 33 Bloor Street East.  Granite installation will occur immediately following completion of the hydro vault work.

Access to all businesses will be maintained and all businesses are open.

Please Note – These construction schedules have been provided by the City and their contractor.  Given the extent and complexity of the project, changes to the schedule may occur.